A work breakdown structure, or WBS, organizes the complete scope of a project into smaller deliverables and work packages. It gives the team a shared picture of what must be produced before they develop detailed activities, estimates, and schedules.
Imagine planning a website redesign. A list containing design, development, and launch looks reasonable, but it leaves important questions unanswered. Who supplies the content? Does the project include redirects, testing, analytics setup, and staff training? How will the client decide that the work is complete?
A useful WBS makes those boundaries visible. This guide explains its components, the principles behind it, and how to create one, using a website redesign example you can adapt to your own project.
What Is a Work Breakdown Structure
A work breakdown structure is a hierarchy that divides the total project scope into manageable components. The overall project sits at the top. Each lower level explains a more specific part of the work until the team reaches work packages it can estimate, assign, and control.
The structure is organized around deliverables: the outputs the project must produce. A deliverable can be an approved requirements document, a tested website, or a training package. It does not have to be a physical product.
The Project Management Institute’s explanation of WBS fundamentals emphasizes decomposing project scope around deliverables. This helps distinguish a WBS from a collection of unrelated actions.
For example, approved website content is an output. Drafting copy, reviewing it, and applying revisions are activities used to produce that output. Both matter, but they serve different planning purposes.
Why Use a WBS in Project Management
Make the Scope Clear                                          Â
A WBS helps stakeholders examine the complete project instead of relying on broad labels. Reviewing the components can uncover missing work, different expectations, and areas where two teams believe the other is responsible.
It also supports scope discussions later. If a client asks for a booking system that was excluded from a simple website redesign, the team can identify the requested addition and assess its implications before committing.
Improve Estimating and Responsibility
Smaller, clearly described packages are easier to estimate than an entire project described in one sentence. The team can consider the required skills, review effort, assumptions, and costs for each part.
Each package also needs a clear point of responsibility. Several people may contribute, but someone should coordinate delivery and resolve questions about its boundaries. Ownership becomes useful when it is tied to a defined outcome and completion criteria.
Support Progress and Cost Review
Work packages provide a structure for comparing planned effort with actual work. When time and costs use consistent references, managers can investigate which part of the project is consuming more resources than expected.
The WBS does not establish deadlines or guarantee delivery. It supplies a scope framework that becomes more useful when connected with scheduling, risk management, and regular review.
Key Components and Levels of a WBS
| Component | Meaning | Website example |
| Overall project | The complete approved scope | Small business website redesign |
| Major deliverable | A substantial output or scope grouping | Approved content and design |
| Smaller component | A more detailed part of a deliverable | Approved page content |
| Work package | A lowest-level component managed as one defined unit | Approved copy for the agreed five pages |
| WBS code | A unique identifier showing the hierarchy | 1.3.1 |
| WBS dictionary | Supporting descriptions and boundaries | Details defining what 1.3.1 includes |
There is no universal requirement for a WBS to have exactly three or four levels. One branch may need more decomposition than another. Stop when the work is clear enough to estimate and manage, while avoiding detail that adds administration without improving decisions.
Larger projects may also use control accounts: management points where related scope, budget, and schedule information is brought together. A small project may not need an extensive control-account system, but it still benefits from consistent package identifiers.
The 100 Percent Rule and Other WBS Principles
Include All the Work Within Scope
The 100 percent rule means the WBS covers all approved project work, and the components beneath a parent collectively account for that parent’s scope. Include internal outputs and project management work as well as the deliverables handed to the customer.
PMI’s guidance on developing effective work breakdown structures explains complete scope coverage and the relationship between the hierarchy and later planning. The rule concerns scope, not keeping employees occupied for every available hour.
Avoid Overlapping Scope
Give each package a distinct boundary. If content upload appears under both content production and website implementation, define where responsibility sits so the same work is not estimated or reported twice.
Some outputs require contributions from several disciplines. That is normal. The goal is to identify where the work belongs, not to force every deliverable into a single department’s organizational chart.
Use Practical Package Sizes
A package should be specific enough for the team to understand its output, estimate its effort, and evaluate completion. A label such as website work is usually too broad. A separate package for every email is usually too detailed.
The often-mentioned 8/80 rule suggests sizing packages within an approximate effort range of eight to 80 hours. Treat it as an optional planning guideline rather than a mandatory standard. Project complexity, reporting needs, and uncertainty should determine the appropriate level of detail.
Deliverable Based and Phase Based Structures
A deliverable-based WBS groups scope around outputs such as approved content, a configured website, and a handover package. This can make acceptance boundaries easier to discuss with clients.
A phase-based structure groups the work under lifecycle stages such as discovery, design, implementation, and transition. Each phase still needs defined outputs and complete scope coverage. Avoid leaving the structure as a series of vague stage names.
Choose an organization that helps the team manage the project consistently. As PMI’s discussion of WBS use across the project lifecycle illustrates, the hierarchy can be represented in different formats while retaining its scope relationships. The order of boxes or rows does not establish activity dependencies.
How to Create a Work Breakdown Structure


Confirm Scope and Exclusions
Review the agreed objectives, requirements, deliverables, and exclusions. Clarify assumptions before decomposition begins. For a website, specify the page count, required functions, supported languages, and whether hosting or ongoing maintenance is included.
An uncertain requirement should be resolved or recorded as an assumption with an owner. Breaking unclear scope into smaller labels does not make it clear.
Identify Major Deliverables
List the substantial outputs needed to complete the project. Include management, review, transition, and handover work where applicable. Ask the people who will deliver and accept the work to review the list.
For the website example, approved requirements, content and design, a built and tested site, and launch documentation are more informative than a list of employee names.
Decompose Each Deliverable
Break the major outputs into smaller components. For approved content and design, the next level might contain approved page copy and an approved design set. Continue where a component remains too broad to estimate or review reliably.
Keep the boundaries consistent. If accessibility checks are included in a testing package, describe them there rather than repeating the same scope under several branches.
Define Manageable Work Packages
Review each lowest-level element. Can the team explain its output, identify responsibility, estimate effort, and decide whether it is complete? If not, refine the description or decompose it further.
A work package can require several schedule activities. The package approved page copy might involve research, drafting, internal editing, and client review. Those activities can be developed when creating the schedule.
Assign Identifying Codes
Use stable codes such as 1.3 for a major branch and 1.3.1 for one of its packages. Codes help connect scope descriptions with estimates, time entries, and reports.
The numbers show where an element belongs in the hierarchy. They do not mean that one package must happen before another. Record timing and dependencies in the schedule.
Document Boundaries and Acceptance Criteria
Create a WBS dictionary entry for each package needing clarification. Describe included work, exclusions, responsibility, assumptions, and what acceptance requires.
Be specific about review limits and inputs. Approved page copy is ambiguous if no one knows who supplies factual information or how many review rounds are included.
Review Completeness and Overlaps
Walk through the hierarchy with delivery staff and relevant stakeholders. Check that child elements collectively cover their parent and that no work is counted twice. Look especially for testing, coordination, documentation, and handover omissions.
Confirm interfaces between packages. For example, the design package may supply approved layouts to implementation, while the content package supplies final copy. Document those inputs without adding duplicate production work.
Approve and Maintain the Structure
Agree the structure through the project’s approval process. In a predictive approach, the approved scope statement, WBS, and dictionary form the scope baseline, as described in PMI’s scope baseline guidance.
When scope changes, assess the effect on effort, cost, timing, and acceptance before updating the approved records. Keep changes traceable so the team knows which version governs the work.
Work Breakdown Structure Example for a Website Redesign
The following example is hypothetical. Assume the project covers a five-page English website, an existing content management system, one contact form, basic analytics configuration, agreed URL redirects, testing, launch, and staff handover. It excludes ecommerce, a booking system, a new brand identity, and ongoing maintenance.
The overall project is 1.0 Website redesign. The table shows its five major branches and lowest-level work packages. Each package’s detailed boundaries belong in the dictionary.
| Major deliverable | Work package codes | Work packages |
| 1.1 Project management and governance | 1.1.1 and 1.1.2 | Approved management plan; status, change, and closure records |
| 1.2 Approved requirements and architecture | 1.2.1 and 1.2.2 | Approved requirements and acceptance criteria; approved sitemap and URL mapping |
| 1.3 Approved content and design | 1.3.1 and 1.3.2 | Approved five-page copy; approved layouts and visual specifications |
| 1.4 Built and tested website | 1.4.1 and 1.4.2 | Implemented staging website; completed test evidence and resolved in-scope defects |
| 1.5 Launch and handover | 1.5.1 and 1.5.2 | Verified production release; training and handover package |
The staging website package includes implementing the approved layouts, loading the final content, and configuring the form and agreed analytics. Content drafting belongs under 1.3.1; it is not counted again during implementation.
The testing package covers the agreed functional, responsive, accessibility, and browser checks. Production verification belongs under the launch package. Define the exact test criteria in the dictionary so these boundaries remain clear.
This example can be displayed as a tree diagram or a numbered outline. A tree is useful for showing relationships; a table or outline is often easier to maintain as descriptions change.
What Is a WBS Dictionary
A WBS dictionary provides the detail behind the hierarchy. Short labels make a structure readable, but they rarely explain everything someone needs to estimate or deliver a package.
The dictionary makes terms consistent. It can record package scope, responsibility, acceptance criteria, resources, milestones, assumptions, and related references. PMI’s overview of work breakdown structures identifies it as the companion detail supporting WBS elements.
Example Dictionary Entry for Package 1 3 1
Package 1.3.1 is Approved five-page copy. The content lead coordinates the work, with client acceptance provided by the designated client reviewer.
Included scope: Research from client-supplied information, draft copy for the five agreed pages, internal editing, and two consolidated client review rounds. The output is a final approved copy document ready for implementation.
Excluded scope: Additional pages, translation, a new brand messaging strategy, and uploading content to the website. Uploading belongs to package 1.4.1.
Acceptance criteria: All five pages match the approved sitemap, factual claims have client confirmation, agreed feedback is resolved, and the designated reviewer has recorded approval.
Estimate and assumptions: An illustrative 24 labor hours, assuming the client supplies complete service information and consolidates feedback. This is an example estimate, not an industry benchmark. The schedule records review dates and dependencies separately.
WBS vs Project Schedule vs Task List
| Planning record | Main question | Typical contents |
| Work breakdown structure | What scope must the project deliver | Hierarchy of deliverables and work packages |
| Project schedule | In what sequence and when will work happen | Activities, dependencies, durations, dates, and milestones |
| Task list | What actions need attention | Individual actions, owners, and statuses |
These records work together. A work package provides a defined piece of scope; the team identifies activities needed to produce it; the schedule then organizes their sequence and timing.
For example, approved layouts is a package. Preparing concepts and revising the selected design are activities. The schedule establishes their dates and how client review affects implementation. A Gantt chart can display that schedule, but it does not replace the scope definition.
How a WBS Supports Estimates Budgets and Time Tracking


Once work packages are defined, estimate the associated activities and roll their effort and costs up to the appropriate package. Use a consistent reference so recorded work can be compared with the estimate.
Suppose package 1.3.1 has an illustrative estimate of 24 hours at an assumed internal labor cost of $40 per hour. Its planned labor cost is $960. If actual work reaches 30 hours at the same assumed rate, labor cost becomes $1,200, a $240 unfavorable variance.
That calculation explains a cost difference, not its cause. Review whether the package had an incomplete brief, additional requests, unexpected research, or internal rework. Separate approved scope changes from estimation error before drawing conclusions.
Actual hours also do not establish percentage complete. Spending 18 of the 24 estimated hours does not prove that the copy is 75 percent finished. Review accepted outputs, outstanding feedback, and remaining effort alongside the time record.
Using project timesheets helps connect employee effort to the appropriate project activities. Establish how those activities map back to work packages so reports can summarize scope consistently. Include project-related expenses when assessing costs beyond labor.
Common Work Breakdown Structure Mistakes
Leaving Out Supporting Work
Teams often remember production but overlook coordination, testing, documentation, and handover. Review how each deliverable will be accepted and transitioned, then account for the required work in the appropriate package.
Creating Vague or Duplicate Packages
Broad labels such as development make boundaries difficult to manage. Overlapping labels create a different problem: double counting. Use dictionary entries to show what is included and where related work belongs.
Confusing Scope With the Schedule
A hierarchy does not explain task sequence. Create the required activities and dependencies after defining the packages. Do not treat the numbering system as a delivery order.
Decomposing Too Far
Excessive detail makes updates burdensome and can distract from meaningful control. Use the level of detail needed to estimate, assign responsibility, and evaluate outputs rather than treating the deepest possible hierarchy as the best one.
Updating Scope Without Reviewing Its Effects
Adding a package may affect several other parts of the project. Review effort, interfaces, budget, and timing before approval. Keep the WBS, dictionary, and related planning records consistent after the change.
Using TimeLive to Track Work Against Your WBS
A WBS establishes the scope framework. Once that framework is approved, TimeLive’s project management capabilities can support tracking work through projects, tasks, time records, and reporting.
Create a consistent mapping between the work packages and the project activities used for time entry. Include identifying codes in supported names or descriptions where helpful, and explain the mapping to employees. Test the reporting structure before using it across the entire project.
Managers can use timesheet approval workflows to review recorded effort and resolve incorrect allocations. Keep deliverable acceptance separate: approving an employee’s hours confirms the time record, while accepting a work package confirms that its output meets the agreed criteria.
Start with one project and check whether managers can trace recorded work back to the right scope component. The useful connection is between what the project promised, what the team did, and what remains to be delivered.
Build a Scope Structure Your Team Can Use
A useful work breakdown structure makes the project understandable enough to estimate, assign, and review. Cover the complete approved scope, give each package clear boundaries, and document how completion will be accepted.
Begin with the major deliverables, review them with the team, and decompose only as far as management needs require. Then connect the structure to the schedule, budget, and actual work records so it remains useful during delivery.
Frequently Asked Questions
What Does WBS Stand For
WBS stands for work breakdown structure. It organizes the total project scope into a hierarchy of deliverables and manageable work packages.
What Is the Main Purpose of a WBS
Its main purpose is to define and organize the complete project scope. The resulting structure supports estimating, responsibility, scheduling, and performance review.
What Is the 100 Percent Rule
The WBS should include all approved project work, with each parent fully represented by its child components. It should neither omit required scope nor add unauthorized work.
How Many Levels Should a WBS Have
Use as many levels as needed to define manageable packages. Different branches can have different depths; there is no universal requirement for a fixed number of levels.
What Is the Difference Between a Deliverable and a Work Package
A deliverable is a verifiable output. A work package is a lowest-level WBS component managed as a defined unit of scope. Larger deliverables may be divided into several work packages, which can each require multiple activities.
What Is a WBS Dictionary
It is the supporting document that explains WBS elements in more detail. Entries can include scope boundaries, responsibility, acceptance criteria, assumptions, and estimates.
Is a WBS the Same as a Project Schedule
No. The WBS defines scope relationships. The schedule sets out activities, their dependencies, and timing. The two should remain connected as the project develops.
Can You Create a WBS in Excel
Yes. A numbered outline with columns for code, parent element, description, and dictionary reference can represent a WBS. Preserve the hierarchy and stable identifiers, and control updates so people use the current version.